Development application D11-012-2022 · Ward 5

156 Miller Drive

site plan

Stage: ClosedOn the record: “CANCELLED”Filed March 28, 2022
“Site Plan Application to facilitate the development of 43 singles (39 units on a private road and 4 freehold units fronting Miller Drive)”
The City of Barrie’s description, in its own words · checked November 28, 2026
The City’s file page

Where it stands

Stage from the City of Barrie’s status, November 28, 2026

The municipality has closed this application file. The record lists what was recorded.

Diagram of the zoning around 156 Miller DriveThe municipality's zoning polygons within about 140 metres of the file's recorded point; the point falls in a zone coded RM2. A diagram, not to scale and not a survey: no building or design is drawn.R1R1R4R4Diagram, not to scaleCity of Barrie zoning and planning open data
Zoning areas around the site; the recorded point falls in RM2 today, which is the zone, not the proposal. Streets show as the gaps between zones. No building or design is drawn. File D11-012-2022.
43
homes proposed
City of Barrie record
1
application in this project: site plan
City of Barrie record
1
dated step on the record; the latest March 28, 2022
Checked November 28, 2026
How we know
Last checked November 28, 2026City of BarrieHow we know
Publisher
City of Barrie
Source dataset
Planning Applications (City of Barrie open data)
Official record
The municipality's own page for this project
Retrieved
November 28, 2026
Licence
Open Government Licence – Barrie (version 1.0) Terms
From the source
the project and application names · file numbers · status · dates where recorded · the description of the proposal
Derived by BarrieIQ
the stage label · grouping of linked applications into one project · area and ward by the site's location · what is nearby · the zoning diagram, from the zoning layer's polygons around the recorded point
BarrieIQ’s words
the summary sentence
Kept current
Rebuilt from the municipality's source by the data pipeline; each run is dated, and changes between runs are listed on the changes page.

Proposed, in the record's words: “Site Plan Application to facilitate the development of 43 singles (39 units on a private road and 4 freehold units fronting Miller Drive)”. Latest dated step on the record: application received, March 28, 2022. File D11-012-2022. As of November 28, 2026 · City of Barrie

Data currency. Read from the City of Barrie source on November 28, 2026. The source publishes no last-edited date. Newest date on any record: November 20, 2026. Planning Applications (City of Barrie open data)

What is being asked

One application

156 Miller Drive is a site plan on the City of Barrie's record proposing 43 homes in Ward 5. It has been closed.

What is proposed

Site Plan Application to facilitate the development of 43 singles (39 units on a private road and 4 freehold units fronting Miller Drive)

The City of Barrie’s description of the application, as published.

The application

As the municipality records it.

  1. Site plan

    D11-012-2022

    Type
    Site plan (Site Plan)
    Status on the record
    CANCELLED
    Received
    March 28, 2022
    Related files (City's list)
    D28-042-2021
    Homes proposed
    43

What has happened

Every dated item on the record
  1. Application received

    Site plan · D11-012-2022 · 2022

Every date in the municipality’s record for this project’s applications, in order. Nothing is inferred between them.

Other projects within 1 km

Development in Ward 5
156 Miller Drive and other planning files within 1 km156 Miller Drive (ringed) and 2 other significant files on the City of Barrie's record within 1 km, over the zoning layer.152 & 156 Miller Drive · Under review · 0 m97 Miller Drive & 275 Pringle Drive · Approved · 420 m1 km around the siteCity of Barrie open data
  • This project
  • Under review (1)
  • Approved (1)
  • 1 km

Statuses as the City of Barrie publishes them; distances straight-line from the file’s recorded point · November 28, 2026

Around the site

156 Miller Drive
Aerial view of 156 Miller Drive, Barrie
Contains information licensed under the Open Government Licence – Ontario

Parks nearby

  • Pringle ParkNeighbourhood · basketball court, playground · 420 m

Schools, heritage and transit

Nearest schools

Transit routes nearby(a published route path within 500 m, as the crow flies)

Distances are between recorded positions, as the crow flies, not walking routes.

What the stages mean

The same words on every BarrieIQ project
Stage: Pre-application
Proposed to the municipality, but a complete application has not yet been received.
Stage: Under review
Filed with the municipality and being reviewed.
Stage: Under appeal
A decision, or the lack of one, has been appealed to the Ontario Land Tribunal.
Stage: On hold
The municipality lists the application as on hold, for example while it waits for more material.
Stage: Approved
The application has been approved. Building may not have started.
Stage: Complete
Final approval has been given or the plan has been registered.
Stage: Closed
The municipality has closed this application file. The record lists what was recorded.156 Miller Drive is here.
Stage: Refused
The application was refused.

Sources

  1. 01City of Barrie page for this project — the current proposal, notices and reports
  2. 02Planning Applications (City of Barrie open data) — checked November 28, 2026

Contains information licensed under the Open Government Licence – Barrie. Open Government Licence – Barrie (version 1.0). Figures are the municipality’s records at the date checked; a later submission can change them.

How we draw the diagram

The shapes are the City’s zoning-layer polygons within about 140 m of the file’s recorded point, simplified for drawing, with their zone codes as published. The tinted shape is the zone the point falls in today. Streets are the gaps between zones. Nothing in the diagram is the proposal: no building, height or design is drawn.

More