When are development charges paid?
Generally at building permit issuance. Under a 24-month pilot that began August 14, 2025, they are calculated and secured when the permit is issued and paid at the earlier of occupancy or two years after the permit. Rental housing of at least 4 units that is not non-profit, and institutional development, can pay in 6 equal annual instalments plus interest starting at occupancy.
Owners on instalments must tell the City within 5 business days of the building first being occupied, or the charges become due immediately.
Source: City of Barrie, Development Charges Brochure: Summary of By-law 2023-074
Can development charge rates be frozen?
Yes. For complete site plan and zoning by-law amendment applications accepted on or after January 1, 2020, the charges are set on the date of the site plan or rezoning application and stay frozen for up to 18 months from the application's approval, with interest added until they are paid. Otherwise, they are set the day before the first building permit is issued. The City lists its current interest rate as 5.45 per cent.
Source: City of Barrie, Development Charges
Are there development charge discounts or exemptions?
Yes. Exemptions include certain affordable housing units, purpose-built second and third suites and some accessory units, and college or university buildings funded by government (not residences). Purpose-built rental buildings of four or more units get 25 per cent off three-bedroom units, 20 per cent off two-bedroom units and 15 per cent off bachelor and one-bedroom units. Industrial expansions of up to 50 per cent of floor area are exempt, and redevelopment within 60 months of a demolition permit earns a credit.
Non-profit institutions developing their own land for their own use get 50 per cent off, or 100 per cent on land leased from or owned by the City.
Source: City of Barrie, Development Charges Brochure: Summary of By-law 2023-074
What was the development charge waiver pilot?
It waived development charges for new residential buildings of five storeys or more that agreed to make at least 20 per cent of units affordable in a purpose-built rental, or 60 per cent in an ownership project, for 25 years. The second intake closed with permit applications due July 15, 2026 and construction started by October 31, 2026. The City reports the pilot is delivering 1,509 new homes, including 303 affordable units, across 10 projects.
Source: City of Barrie, Development Charge Waiver Pilot Program